How Long Does the Application Process Take on Average?

AI Summary

The application process for planning permission in Harrow typically takes eight weeks for most applications and extends to 13 weeks for larger or more complex developments. This timeline begins once the application is registered.

Here’s a quick overview:

Application Type Timeframe
Standard Applications 8 weeks
Large/Complex Applications 13 weeks
Non-material Amendments 28 days

It's a good idea to ensure all documents and payments are correct when submitting your application to avoid delays. For more details on how to apply, you can visit apply for planning permission.