The application process time can vary depending on the type of application you're submitting. Here’s a summary of the key application types and their respective processing times:
| Application Type | Processing Time |
|---|---|
| Householder and minor development | 8 weeks |
| Major development | 13 weeks |
| Environmental Impact Assessment | 16 weeks |
| New Houses in Multiple Occupation (HMO) | 18 weeks |
| Selective Licences (before 1 Sept 2024) | Up to 12 months |
| Selective Licences (after 1 Sept 2024) | Up to 16 weeks |
| New Premises Licence | At least 6 weeks, potentially up to 2 months |
Keep in mind that these times are targets, and various factors can cause delays. It’s a good idea to check with the council if you’re approaching these timelines without an update.