If your application has not been processed within three months, you should reach out to the council for an update. The delays are acknowledged due to a high volume of applications and a new software system implementation, which might have impacted processing times.
If your application falls under the typical decision timelines, here’s a quick overview:
| Application Type | Statutory Target Timescale | Current Average Determination |
|---|---|---|
| Major | 91 days | 281 days |
| Minor | 56 days | 171 days |
| Other/Householder | 56 days | 89 days |
| Non-material amendments, permitted development | 56 days | 74 days |
For the best course of action, consider contacting your case officer or emailing the planning team at planning.applications@tmbc.gov.uk. If you need more information, you can also view your application status here.