How Long Does the Application Take?

AI Summary

The duration of a planning application process in West Berkshire generally depends on the type of application being submitted. Here's a summary of the expected timelines for various application types:

Application Type Decision Timeframe
Full planning permission for non-major development 8 weeks
Full planning permission for major development 13 weeks
Householder development (extensions, etc.) 8 weeks
Full planning permission for non-major minerals and waste 8 weeks
Full planning permission for major minerals and waste 13 weeks
Outline planning permission for non-major development 8 weeks
Outline planning permission for major development 13 weeks
Prior approval (various types) Typically 4-8 weeks
Discharge of conditions 8 weeks
Advertisement consent 8 weeks
Request for Screening Opinion 3 weeks
Request for Scoping Opinion 5 weeks

The application will be registered and acknowledged within five working days of submission. If you're considering submitting a planning application, it may be beneficial to utilize the pre-application advice service for tailored insights and better preparation.