The approval time for planning applications in Dartford varies based on the type of application. Here's a breakdown of the standard statutory time limits:
| Application Type | Approval Time |
|---|---|
| Major Development | 13 weeks |
| Technical Details Consent | 10 weeks |
| Public Service Infrastructure Development | 10 weeks |
| Other Types of Development | 8 weeks |
| Applications requiring Environmental Impact Assessment | 16 weeks |
Initial validation usually takes up to 5 working days, followed by a consultation period of 21 days. If more time is needed to assess an application, an extended determination period can be agreed upon in writing. For more information, you can check out the full details on decision-making.